Six stages, and what goes wrong at each one

Every stage below states what you receive, what is needed from you, and the thing that most commonly derails it. The last of those three is the part no process page usually admits to, and it is the part worth reading.

The six stages

  1. 01

    Site assessment

    One visit, typically 2–3 hours

    I visit the site, measure the roof or ground area, check your sanctioned load and phase against the connection agreement, look at shading through the middle of the day, and read twelve months of bills. Nothing is quoted before this happens, and if the assessment concludes that solar does not justify itself on your site, that is what I will tell you.

    You receive
    Load profile, shading assessment and an honest recommendation
    Needed from you
    Twelve months of bills, your connection agreement, and access to whoever actually knows the operating hours
  2. 02

    Design

    3–7 days after assessment

    The array and inverters are sized against your measured daytime consumption rather than your roof area. You get a single-line diagram, string layout, cable and protection sizing, earthing design and a structural loading check — and a bill of materials specified to model number, so that a substitution later would be visible.

    You receive
    Single-line diagram, structural check and a model-specific bill of materials
    Needed from you
    Approval of the design before anything is purchased, and a decision on whether outage backup is required
  3. 03

    Procurement

    1–6 weeks, set by inverter lead time

    Equipment is bought at wholesale market prices from suppliers I have worked with for years. Every invoice reaches you in the supplier own name, dated and itemised. I take no margin on any of it, and I verify what physically arrives against what was ordered — model numbers, serial numbers and counts.

    You receive
    Original supplier invoices, and delivery verified against them
    Needed from you
    Payment to suppliers directly, at the prices on their own invoices
  4. 04

    Installation

    3 days to 4 weeks by scale

    Teams I have worked with for years, available at around 24 hours notice, working around your operating hours where the site cannot stop. I am on site personally for the stages that decide whether the system lasts twenty years: structure anchoring, roof penetration and waterproofing, DC termination and earthing.

    You receive
    Progress photographs and site reports as the work proceeds
    Needed from you
    Site access, and agreement on the one unavoidable outage window
  5. 05

    Commissioning

    1 day, plus the DISCO timeline

    String-level generation verification, anti-islanding testing to IEC 62116, and documented test results. The net metering or net billing application with your distribution company runs alongside from day one rather than starting here, and I attend the inspection personally.

    You receive
    Commissioning certificate, test results and monitoring access in your own name
    Needed from you
    Documents for the DISCO file, and availability for the inspection
  6. 06

    After-sales

    Ongoing

    Generation checks, fault diagnosis and manufacturer warranty claims, handled by the engineer who designed and commissioned the system. Included on projects I deliver rather than sold afterwards as a service contract. I do not publish a guaranteed response time in hours, because I am one engineer and a number I could not honour would be worse than none.

    You receive
    Warranty register with expiry dates, and a direct number
    Needed from you
    A call when a reading looks wrong, rather than waiting for it to get worse

Questions

What clients ask about the process

What happens at a solar site assessment?
I measure the roof or ground area, check your sanctioned load and phase against the connection agreement, assess shading through the middle of the day, and read twelve months of bills to establish what you consume between roughly 9am and 4pm. It usually takes two to three hours. Nothing is quoted before it happens, and if the conclusion is that solar does not justify itself on your site, that is what the assessment says.
What do I need to provide before you can quote?
Twelve months of electricity bills rather than one, your connection agreement showing sanctioned load and phase, and access to whoever genuinely knows when the heavy equipment runs — in a factory that is usually a foreman rather than an owner. Seasonality and real duty cycles are most of the picture and neither appears in a single bill.
How many times will you actually be on site?
At assessment, at the stages that decide whether the system lasts — structure anchoring, roof penetration, DC termination and earthing — at commissioning, and at the DISCO inspection. I am not present for every hour of installation, and I would not claim to be. What I am present for are the points at which a mistake becomes permanent or invisible.
Can I make changes to the design after approving it?
Before procurement, easily. After equipment has been ordered, it depends on what changed — a string layout adjustment is straightforward, while deciding you now want battery backup usually is not, because storage is an inverter decision made at design stage. This is why the design approval step exists as a distinct gate rather than a formality.
What do I actually receive at handover?
Original supplier invoices in the supplier own names, the as-built single-line diagram, structural and protection documentation, commissioning test results including anti-islanding verification, the warranty register with every expiry date, and monitoring access registered in your name rather than mine. A system documented that way can be picked up by any competent engineer; an undocumented one is the one that becomes stranded.

Next step

It starts with stage one

A site assessment, twelve months of bills, and an honest answer about whether the rest of these stages are worth running at all.